Project Management

 Complete Parts 1 and 2 of the Red Zuma Project, the information for which is located in Appendix 2 in the back of the book. You will need to turn in the Microsoft Project File along with the requested printouts and reports.  It is important for you to present this information in a professional manner as if you were turning this into your supervisor.  Therefore, make sure that your memo looks and is written in a professional manner and tone.  Your memo will be written with a word processing software like MS Word.  Your response should be concise, but with the appropriate detail that this type of task would require in a professional setting. 

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

Red Zuma Project

The ARC Company specializes in developing and selling a wide range of high-quality scooters. Sales representatives report that there is a growing demand for racing scooters. ARC’s president, Robin Lane, is excited about the possibilities and predicts that one day these kinds of razor scooters will be featured in X-Game events. ARC is a small company and uses a strong matrix to optimally utilize limited manpower.

The Project Priority Matrix for the Red Zuma Project is:

Part 1

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

You are a member of a project team assigned to develop the new razor scooter code named “Red Zuma.” Table A2.5 contains the information necessary to create a project schedule. For the purpose of this case assume the following:

TABLE A2.5 Red Zuma: Project Schedule

1. The project begins January 2, 2015.

2. The following holidays are observed: January 1, Martin Luther King Day (third Monday in January), Memorial Day (last Monday in May), July 4th, Labor Day (first Monday in September), Thanksgiving Day (4th Thursday in November), December 25.

3. If a holiday falls on a Saturday, then Friday will be given as an extra day off, and if it falls on a Sunday, then Monday will be given as a day off. If December 25th falls on a Friday then Monday will not be given a day off.

4. The project team works eight-hour days, Monday through Friday.

Page 622

Construct a network schedule for this project and prepare a memo that answers the following questions:

1. When is the project estimated to be completed? How long will the project take?

2. What is the critical path for the project?

3. Which activity has the greatest amount of slack?

4. How sensitive is this network?

5. Identify two sensible milestones and explain your choices.

Include the following printouts:

· A Gantt chart.

· A network diagram highlighting the critical path.

· A schedule table reporting ES, LS, EF, LF, and slack for each activity.

Part 2

The following personnel have been assigned full-time to the Red Zuma project team:

4 marketing specialists

4 design engineers

4 development engineers

4 industrial engineers

4 test riders

2 purchasing agents

Use the file from Part 1 and the information contained in Tables A2.6 and A2.7 to assign resources to the project schedule.

Part A

Prepare a memo that addresses the following questions:

1. Which if any of the resources are overallocated?

2. Assume that the project is time constrained and try to resolve any overallocation problems by leveling within slack. What happens?

3. What is the impact of leveling within slack on the sensitivity of the network?

Include a Gantt chart with the schedule table after leveling within slack.Page 624

4. Assume that the project is resource constrained and no additional personnel are available. How long will the project take given the resources assigned? (Hint: Undo leveling performed in Part A before answering this question.)

Note: No splitting of activities is allowed.

1. How does the new duration compare with the estimated completion date generated from Part 1? What does this tell you about the impact resources can have on a schedule?

Include a Gantt chart with a schedule table displaying free and total slack depicting the resource-constrained schedule.

Part B

Top management is not happy with the resource-constrained schedule. Robin Lane, the president, has promised retailers that ARC will begin production in time for the major trade show in Las Vegas on January 22, 2016, which means the project needs to be completed by January 17, 2016. She has authorized working the first available Saturday of each month to help the project get completed sooner. She realizes that this will only reduce the project duration by 12–13 days.

After talking to the engineers, everyone agrees that they do not have to wait for the Detailed Product Design to be 100% completed before starting to build the prototype. The consensus is that Building the Prototype can start 30 days after the start of the Detailed Product Design. Likewise the Final Manufacturing Process can start 15 days after the start of Finalized Product Design.

Dewey Martin, director of product development, is also willing to add personnel to the project. He is willing to make available at least one more Development, Design, and/or Industrial Engineer to the project as well as Marketing Specialist. Since there is an acute shortage of personnel at ARC he requests that you only use additional manpower that will help meet the deadline. Your objective is to develop a schedule which will satisfy the deadline with minimum additional resource usage.

Prepare a memo that addresses the following questions:

1. What was the impact of introducing Start-to-Start lags to the schedule and budget?

2. Which, if any additional personnel assignments, would you choose to complete the project before the January 17th deadline? Explain your choices as well as the reasons for not choosing other options.

3. How have these changes affected the sensitivity of the network and the critical path?

Include a Gantt chart with a schedule table displaying free and total slack for the new schedule.

Note: Do not assign new personnel to specific tasks, simply add them to the Resource Sheet. All new personnel are available full time (100%).

Calculate your order
Pages (275 words)
Standard price: $0.00
Client Reviews
4.9
Sitejabber
4.6
Trustpilot
4.8
Our Guarantees
100% Confidentiality
Information about customers is confidential and never disclosed to third parties.
Original Writing
We complete all papers from scratch. You can get a plagiarism report.
Timely Delivery
No missed deadlines – 97% of assignments are completed in time.
Money Back
If you're confident that a writer didn't follow your order details, ask for a refund.

Calculate the price of your order

You will get a personal manager and a discount.
We'll send you the first draft for approval by at
Total price:
$0.00
Power up Your Academic Success with the
Team of Professionals. We’ve Got Your Back.
Power up Your Study Success with Experts We’ve Got Your Back.

Order your essay today and save 30% with the discount code ESSAYHELP