Project 2-6: Don Funk Music Video Problems
A student who is interning with your company made some updates to the music video
project schedule. Unfortunately, he is still learning about Microsoft Project and has entered
some information incorrectly. You need to correct the problems with the project schedule
before distributing it to your team.
OPEN Don Funk Incorrect 2-6 from the data fi les for this lesson.
1. Review the Resource Sheet for this project schedule.
2. Based on what you have learned in this lesson about Resource Types, Maximum Units,
and Standard Rates, fi nd the resource errors in this project schedule and make
corrections to them. (Hint: There are three resource errors in the project schedule.)
3. Study the last three resources on the sheet. If dry ice is a work resource and bottled
water is a cost resource, make corrections to the information given for these resources
(estimate the rate if necessary).
4. SAVE the project schedule as Don Funk Corrected and then CLOSE the fi le.