The Bamínica Power Plant Project

Read the “The Bamínica Power Plant Project” case study in your textbook, and submit answers to all the questions that follow the case study.

part five I N T E G R A T I N G C A S E 1

The Bamínica Power Plant Project: What
Went Wrong and What Can Be Learned

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

This project was like the Hotel California. “You can check out anytime you want but
you can never leave.”

There were several times along the way where we could have stopped the proj-
ect but we did not have the willpower, discipline, or maturity to do it…. There was
no single fatal flaw in the project. There were a bunch of things that made it ugly at
the end of the day…. My view is that when you do things at the speed of light you
don’t have time to read the warning signs.

We allowed a transaction to go through that had a lot of pieces that should have
been more heavily scrutinized and fixed because we were very hungry for a deal.
The people in charge weren’t able to identify all the risks. The people who could
have done that were pushed away from the transaction.

Various Comments from a Bamínica Project Developer

T
om Stephens, Executive Vice President, Global Development for Power-
Gen Inc. (PowerGen), was evaluating the company’s eight-year involve-
ment in the Bamínica power plant project, which was now operated by a
joint venture controlled by PowerGen. Stephens considered the Bamínica

power plant one of PowerGen’s most diffcult and challenging projects. There had
been problems in many different areas, including site selection, joint venture man-
agement, fnancing, plant construction, equipment suppliers, community relation-
ships, and customer payments. Although the power plant was proftable, the
various problems had consumed a disproportionate amount of PowerGen manage-
ment time given the size of the project. As Stephens reviewed the project’s history
and many challenges in mid-2011, he hoped he could identify some key learning
areas to apply to future projects.

PowerGen
PowerGen, Inc., a global power company with generation and distribution busi-
nesses, operated across fve continents. Founded in 1987 in Houston, Texas, Power-
Gen built its first power plant in 1989 in Louisiana. Over the next six years,
PowerGen built four more plants in the United States. The company then began
looking for international opportunities.

In the early 1990s, global markets for power plant projects began to open up.
PowerGen built its first plant outside the United States in Argentina and then
expanded to the United Kingdom, Indonesia, China, Hungary, Brazil, Ghana,
Cameroon, and several Caribbean nations, including Bamínica. Although most of
the power plants used thermal fuel sources, in 2011 the company was actively

Copyright © 2011 Thunderbird School of Global Management. All rights reserved. This case was prepared by
Professor Andrew Inkpen for the purpose of classroom discussion only, and not to indicate either effective or
ineffective management. Various place, company, and individual names, including PowerGen, and other infor-
mation are disguised.

involved in a range of projects using renewable fuel such as biomass, hydropower,
solar, and wind.

Electricity Supply in Bamínica
Bamínica, a Caribbean nation with a population of about 4.5 million, had
experienced robust economic growth from 2002 to 2007. During the 2008 to
2009 period, growth slowed to about 3.0% and then picked up to about 7% in
2010. Economic growth was led by exports from free-trade zones and strong
performance from the construction and economic sectors. However, there
was an estimated 150 MW defcit in electricity generation capacity and power
outages were frequent. It was common for businesses in Bamínica to maintain
backup power systems and it was acknowledged that problems with power
were hampering economic growth. The head of the power company, the
Corporación Bamínica de Electricidad (CBE), admitted that because of old
equipment, problems with billing, and widespread power theft, only about
60% of the power actually produced was paid for. The CBE was operating on
a deteriorating asset base and could not keep up with growth in demand.
CBE’s cost was about 12-15 cents/kWh. Electricity demand was expected to
grow 9% over the next decade. Private power projects were necessary if electricity
demand was to be met.

Overview of the Bamínica Project
The project was a barge-mounted 185 MW combined cycle baseload plant located
at Puerto Salinas on the north coast of Bamínica. The project would be one of the
largest privately owned, project-fnanced power plants in Latin America and, when
completed, provided more than 20% of the country’s average electric generation
capacity. The project was owned by PowerGen/Jones Cogeneration Limited Part-
nership (PJCLP), a joint venture between PowerGen and Jones International (JI).
Originally, each partner had a 50% ownership interest. In 2011, JI’s ownership was
15% and PowerGen’s share was 85%.

The plant was mounted on two seaworthy barges. One barge contained a 138k
kV substation and a Western Electric 75 MW turbine generator designed to burn
No. 2 diesel fuel. The second barge contained a Waste Heat Recovery Steam
Generator, two auxiliary boilers, and a 110 MW Western Electric steam turbine
generator. The boilers burned No. 6 fuel oil. Seawater was used for cooling and
then discharged into the sea outside the port area. The shore facilities included
2 � 60,000 barrel No. 6 fuel oil tanks, 2 � 60,000 barrel No. 2 fuel oil tanks, a
fuel pumping facility, a utility-pipe corridor, a fuel unloading facility, a parking
area, space for a cooling water discharge line, and office space. The project met
all local and World Bank environmental standards.

The sole power purchaser was CBE, a general utility with generation, transmis-
sion, and distribution in Bamínica. The power purchase agreement (PPA) had a
19-year term and was structured in U.S.-style, with energy payments that allowed
for pass-through to CBE of all fuel costs at market prices and operations and main-
tenance and capacity payments intended to cover all other project costs and pro-
vide a return on investment. The Bamínica government guaranteed the peso (the
local currency) convertibility and all CBE obligations under the PPA agreement
and further supported the guarantee by providing a $24 million letter of credit.
CBE payments were dollar denominated.

Integrating Case 1 The Bamínica Power Plant Project 685

The project cost was $204 million. Long-term debt for the project consisted of
loan agreements with International Finance Corporation (IFC) and several other
lenders, including government development banks of Germany, Holland, and the
U.K. The plant became operational in simple cycle mode in 2004 and in combined
cycle mode in 2006.

Project Initiation
PowerGen first became interested in Bamínica in early 2003. Several PowerGen
people, including Don Williams and Jack Kirk, went to Bamínica on an exploratory
visit. Williams and Kirk worked in PowerGen’s development group, which was
responsible for initiating and constructing projects. Williams, an engineer, was in
his late 50s and had worked for various energy companies over his career. Kirk
was a former U.S. military offcer and was in his late 30s. Prior to joining PowerGen
two years earlier, he had not had any private sector experience.

In April 2003, Williams returned to Bamínica and spent a week driving around
the country. His objective was to learn as much as he could about Bamínica cul-
ture, the government, the land, other power plants, and business prospects.
Based on that trip, the development team decided that PowerGen could poten-
tially develop a diesel-powered plant of about 150 MW on the north coast.

The CBE encouraged PowerGen to make a proposal. With Jack Kirk in charge,
PowerGen began preparing a proposal for the CBE. Kirk was responsible for devel-
opment in Central America and the Caribbean. Prior to joining PowerGen, Kirk
was a colonel in the U.S. Army. He had no project development experience or
business background. Kirk joined PowerGen in 2001 and had not yet closed any
deals.

In July 2003, just a few days before the proposal was to be submitted, the team
discovered that Jones International (JI) and the CBE had signed an agreement in
March 2003 to develop a power plant on the north coast. At this point PowerGen
knew nothing about JI, a company run by Richard Jones as a one-man business. JI’s
only previous development was a 200 MW cogeneration facility running on natural
gas in Texas. The proposed Bamínica facility would be a copy of the Texas plant
but built on barges.

The PowerGen team concluded that there was room for only one plant on the
north coast, so ceased work on their proposal and left Bamínica. In August 2003,
Don Williams called Richard Jones. PowerGen knew that JI had signed a PPA with
the CBE and had an obligation to secure a construction contract within a certain
period of time. Suspecting that JI did not have the capital to develop the project,
Williams thought that perhaps JI and PowerGen could work together. The conver-
sation went as follows:

PowerGen (Williams): We want to congratulate you on your win with the CBE.

Jones: Thank you very much. I had heard about you guys and knew you were in
competition against us.

PowerGen: Perhaps there is something we can do to cooperate.

Jones: I already have the PPA. Why do I need you people?

PowerGen: Well, the PPA has a pretty short window for fnancing—maybe we
can fnd some way to help?

Jones: Thanks, but I already have the PPA and I don’t anticipate any problems
getting fnancing.

686 Part 5 Integrating Case 1

PowerGen subsequently learned that Jones had been to about 15 banks and
none were interested in financing the project. In late August, two-and-a-half
weeks after the initial PowerGen-Jones conversation, Jones called PowerGen and
suggested a partnership. According to Williams:

Richard Jones sent us a confidentiality agreement to sign and it was the most screwed
up agreement you have ever seen. We should never have signed it. Although the
agreement never caused us any problems, it was defnitely a red flag in the way it was
drafted.

There were lots of problems with the PPA. Richard Jones went to Bamínica and
got most of them fixed. In the end the PPA was not bad. But, combined with a cus-
tomer who interpreted it differently than us and the problems with the plant, it was a
disaster.

We were probably Jones’s last resort. We had the ability to finance the whole proj-
ect out of cash. That was one of the attractions. We told Richard that if we liked the
project, we would use PowerGen’s cash and put it together on a fast track basis.
When we went to the board we were confdent that we could finance this thing out.

In October, PowerGen received board approval to proceed with a joint venture
with JI. In November, without notice to PowerGen, Jones executed a turnkey con-
struction contract with Western Electric for $117.25 million.

It was a bad construction contract that we immediately tried to change for the benefit
of the owners. It was so one-sided it was leaning over. The only right the sponsor had
was to pay. Jones said that he had to sign with Western Electric because he had a
time limit to perform in the PPA. We tried to get Western Electric to make changes
but they basically folded their arms and said no. For example, I wanted the operations
and maintenance manuals in Spanish. Western Electric said no. Western Electric
would not let us review contract details and our management refused to dig
their heels in. At the end of the day, Jones and Western Electric colluded to get what
Western Electric wanted.

Throughout this period there were various opportunities for PowerGen to kill the
deal but nobody did because the expected returns were off the charts.

Jack Kirk had a very free hand in developing the project and was under pres-
sure to complete a deal. That was usual in PowerGen. Developers were expected
to find and close deals and were incentivized to do so. Bonuses tied to projected
project performance were a signifcant share of developer compensation for energy
infrastructure projects. Developers who did not close deals and finish projects
rarely lasted long at PowerGen. Bonuses were typically paid at two stages: at the
completion of project fnancing, and at the start-up of the project. Lead project
developers determined how the bonus was shared across the development team.

Kirk was running around unsupervised because we had various other bigger deals
under way. As well, Kirk was trusted. He was a guy with ice water in his veins. He
was not afraid to stand up to the Bamínica government. You did not have to be around
him long to have confidence in him. He seemed to have the capabilities of a PowerGen
developer.

Prior to the Bamínica deal, Kirk worked on a project in Colombia that did not
get PowerGen approval. Because he was a senior developer and had not yet closed
any deals, “Kirk’s future was largely dependent on the Bamínica project.”

During the negotiation process, Jack Kirk made all the decisions and put the package
together. He listened to everybody but at the end of the day he was the driver. Jack
called the shots and had a pretty free hand. Once it was put together and the outside
counsel and the finance people were brought in, then it went to the board.

Integrating Case 1 The Bamínica Power Plant Project 687

This view of Kirk’s autonomy is refected in comments from another PowerGen
manager who had some involvement early in the deal:

I took a strong position on several points. I thought we were going in the wrong direc-
tion in that (a) we were creating a situation that was unstable, and (b) we were over-
paying and giving Jones too much for what he was bringing to the table. I said we
needed to be more aggressive in designing the joint venture and particularly who con-
trolled the venture, and insisting on changes to the PPA and the construction contract.
In terms of experience, slickness, business sophistication, street smarts, and a willing-
ness not to be constrained by normal ethical standards, Jones had us at a disadvan-
tage. I thought we needed some more experience on our team. Kirk had been pretty
successful in the military and was used to running his own show. He did not like inter-
ference from other people. He went to Rebecca [the head of PowerGen Latin America]
and said, “I want this guy off my back.” So, I was overruled.

The Partnership Agreement
Within PowerGen, Richard Jones quickly developed a reputation for being diffcult
to deal with and a somewhat unusual personality:

Richard Jones is an unbelievably crazy guy. You match up a wild man who believes his
own b.s. with a developer who is desperate for a deal, and what do you get? We did a
bit of research on Jones and learned through various law frms that he was very liti-
gious. It turned out to be true. Richard would say in letters to us that “You will recall in
our last meeting that we agreed a, b, c.” when in fact we agreed x, y, z. We had to
respond to everything he did, almost on a daily basis.

It was a very diffcult negotiation with Jones. Because of that we didn’t have as
strong a partnership agreement as we should have. When the deal was cut, we did
not have a lawyer sitting there full time. Part of the problem was the inexperience of
Jack Kirk. There were no other deals in Latin America at that time and there was a lot
of pressure to get this one going.

In late November, PowerGen and JI signed the agreement for the PowerGen/
Jones Cogeneration Limited Partnership (PJCLP). According to the agreement,
PowerGen Construction would oversee construction.

We knew there were problems with the construction contract. Jones thought he understood
the risks because he had developed a plant in Texas. We knew that if we were interested in
this transaction, we needed to get control very quickly over the unilateral decisions being
made. We entered into a partnership agreement under which PowerGen was able to get
vast control so that the project could get financed. As long as PowerGen had to front the
money for Jones, the concept was that after the banks converted their construction finance
to non-recourse project finance, we would try to control the project.

Even though the construction contract was signed between Jones and Western
Electric, our outside lawyer told us not to sign. We stayed up all night with Western
Electric and Sylvanto [Western Electric’s construction partner] making changes to get
the contract to the bare minimum. But, with the returns, we thought we could live with
it. We also kept telling ourselves that Western Electric was a marquee company and
they’d do the right thing. Wrong, big mistake. Western Electric was trying to make
money selling turbines and they would shove them down your throat.

In the final negotiations with Jones, we tried to get him to make two representations:
one, that the PPA was legal, valid, and enforceable under Bamínica law; and two, that
there were no FCPA violations. We told Jones that he had to bear the risk if any of his
people bribed someone. Jones did not like that. We also told him that if the PPA was not
enforceable, it was also his problem. In the end we got weaker representation on these
issues than we should have.

688 Part 5 Integrating Case 1

It also became apparent to us that Jones was going to ride our coattails and that
this was a mouse on the coattails of an elephant. We tried not to act like an elephant
but he continually used that against us. He’s a crafty guy and he played us like a piano
for a while.

Partnership Details
The agreement was set up with PowerGen and JI each holding a 1% general partner
interest (see Exhibit 1 for ownership structure as of 2011). Both partners initially
had a limited partner interest of 49% each. Richard Jones’s stake was subject to
reduction unless he came up with a certain amount of money at financial close to

EXHIBIT 1
Jones/PowerGen Cogeneration Limited Partnership after Jones 35% Equity Share
Transferred to PowerGen

(1) Operations, Maintenance and Admin. Services Agreement
(2) Fuel Supply and Management Agreement
(3) Turnkey Construction Contract
(4) Electric Energy Supply and Sales Contract
(5) Technical Services Agreement
(6) Same Ownership Structure as Smith/Enron Cogeneration
Limited

Partnership

Operational Diagram Ownership Diagram

PowerGen
Corp.

Western
Electric

Company

Corporation
Barbuda de
Electricidad

Electricity (4) Turnkey
Contractor (3)

Jones/PowerGen
Cogen. Ltd.
Partnership

(Turks & Caicos)

Asset

Technical
Services (5)

Operator (1)

Fuel Supplier (2)

PowerGen
Barbuda

Operations,
Limited

PowerGen
Barbuda
Limited

Jones
Cogen

Jones/PowerGen
Cogeneration Limited

Partnership

1% G.P.
14%

L.P.

1%
G.P.84%

L.P.

100%

PowerGen
Fuels

International
Inc.

Jones/PowerGen
O&M, L.P.

(Turks & Caicos)

PowerGen
Power

Operating
Company

100%

Integrating Case 1 The Bamínica Power Plant Project 689

repay PowerGen for carrying his out-of-pocket equity from inception to financial
close (the stake was subsequently reduced). The agreement provided the following:

1. Each partner will always agree and discuss major issues, except for financing,
which was exclusively in PowerGen’s control.

2. Unanimous approval of the partners required for: liquidation, sale of the busi-
ness, changing the name of the company, entering into agreements with part-
ner affliates, modifying the construction budget upwards, and modifying the
distribution of development fees.

3. For all other decisions, Jones and PowerGen will collaborate.

Notwithstanding the PowerGen supervote for financing, Jones’s de facto involvement
from the beginning was that he acted like a 50% shareholder. As well, “Until the
financial close, PowerGen bent over backwards to accommodate Jones’s concerns, to
a fault. After the fnancial close, we no longer had to be so accommodating.” Also,
the agreement did not include clear exit terms, something that would become
contentious at a later date.

Site Selection
According to the PPA, the government was to provide a site for the project and
provide the necessary regulatory authorizations. The government provided a site
near Puerto Salinas. The site was inadequate because it would require tearing
down an old bodega on the waterfront. The local government objected to the
development because they had their own plans for the area. So, another site had
to be found quickly because there were time deadlines in the PPA. Simple cycle
power had to be available by May 2004.

Some people said that since the site was not suitable, the clock should roll over until
we found a site. Some of us were not comfortable with this view. We had already
given the order to Western Electric. The turbine and the barge were being built. God
forbid that the barge arrives and we don’t have a site. There were not a lot of choices
for sites. We looked farther away from Puerto Salinas but that would have meant build-
ing a transmission line, which would have been very diffcult.

Another site was located but it also had problems. Finally, a third site that CBE recom-
mended was found. It was zoned for industrial use with the approval of the Bamínica gov-
ernment and the CBE against the protests of a nearby hotel. The site was at the western
edge of a bay on the leeward side of a port. The hotel was on a ridge, north of the plant
in a straight line. The design of the plant included exhaust stacks which were about the
same height as the hotel restaurant. When the plant was under construction and during
the testing phase, there was a lot of noise throughout the day and night because silencers
were not included in the design of the steam relief system. In addition, although the
emissions normally blew to the south, away from the hotel, there were times when the
wind shifted and the emissions blew north over the hotel. Just beyond the hotel was an
upscale residential neighborhood occupied primarily by foreigners.

We did a lot of emissions modeling to assure ourselves that we would not cause any
problems. Our greatest concern was noise from the steam blows and the aesthetics of
the property. We spent a great deal of money on landscaping and painting the tanks. We
tried to make the place attractive. The folks at the hotel liked what we did but they did not
like the noise. And, I believe the operators ignored directions and did a steam blow
when the wind was blowing directly over the hotel. We never knew for sure if the particu-
late fallout came from our plant or other plants about a mile and a half across the bay.

690 Part 5 Integrating Case 1

Construction
The PowerGen development team was responsible for completing the construction
and then turning the plant over to PowerGen’s asset management group. There
were construction problems from the beginning, leading to a series of disputes
and arguments between PowerGen and the contractors. For example, one dispute
began like this:

In your own [Western Electric] literature you say that it is preferred that the client put in
fuel treatment, which means centrifuges. I said to Western Electric, “Where is the
centrifuge.” Western Electric said we don’t need one and it was not included in
the price. If you want one, you pay for it. So we did, for more than a half million dollars.
The proposal that Western Electric signed had dual fuel filters. When we got the actual
unit it had one filter. Western Electric said that they changed their standard. I had to buy
them myself. Before they were installed I can’t count the number of days that we had to
shut the plant down because the fuel filter was plugged. They just dug their heels in and
said we are Western Electric and we do it this way.

We initially thought we would not have to do a lot of oversight. We were reasonably
confident that the contractors would deliver. We had never worked with Western
Electric before this project. We had good feelings about them—they were supposed to
be a first-rate company.

To satisfy the lenders, PowerGen’s construction company oversaw the construc-
tion. Unfortunately, Power-Gen overlooked some serious construction issues and
Jack Kirk was not interested in hearing about construction problems. Then, Kirk
left the company to join a competitor.

Our own PowerGen construction guys were not leading the parade; they were stand-
ing on the curb watching the parade go by with full confidence that we’ve got the best
in the world and they are going to do it right. Unfortunately, Western Electric did not
have their A team on the ground. They were under pressure to get things done quickly
so they cut corners. I didn’t figure this out until late in the game. They did a sloppy job.

We were also under pressure to get the project finished. For one thing, we had contrac-
tual deadlines that we had to meet. The project was to be transferred to PowerGen Global
Power and we were told to stop screwing with the project and get it transferred over.

Throughout the construction phase, Richard Jones and his company did little or
nothing. Richard was always the missing man. He was off sailing his sailboat or hunt-
ing or fishing. He might return our call or he might not. He wanted to be part of the
decision-making team but he was never around to make a decision.

The Project Start-up
The project was designed in two phases. The frst phase was a simple cycle power plant
on a barge that generated about 75 MW. This phase was completed six months after
the contract was signed. The second phase was a combined cycle power plant that
included two boilers. This phase was supposed to be completed by June 2005.

The second barge was brought in, and when the performance test was run,
there was major failure in the gas turbine and boilers. The result was a lengthy
period of repair and disputes with the contractors. It was several months before
the cause of the problem was identifed and the repairs were completed. PowerGen
concluded that contaminated water and other anomalies were present in the prep-
aration for the start-up. Water quality, something Western Electric should have
controlled, was not carefully monitored during commissioning and the boiler suf-
fered extensive corrosion damage.

Integrating Case 1 The Bamínica Power Plant Project 691

There were major disputes with Western Electric and Sylvanto about who was
responsible for the installation problems, why they occurred, and if claims were
under warranty or not. There was a major insurance issue because of a lapse in
coverage. It was unclear if a major claim was a Western Electric/Sylvanto responsi-
bility or a PJCLP responsibility.

Construction problems delayed the second phase start-up until January 2006.

Financing
PowerGen committed to a very aggressive deadline to have the power plant oper-
ating. PowerGen financed the initial development, with the understanding that
long-term non-recourse financing would replace PowerGen’s debt. From the
beginning, Bamínica was acknowledged as a diffcult place to get projects financed
because (1) the government had a history of not paying its debts; (2) there was a
thin foreign exchange market; and (3) there were weak banking laws.

The project was designed to be 25% equity and 75% debt. The original cost was
$204 million and the goal was to raise $153 million. The plan was to have a single
financial closing with two lenders: the World Bank’s International Finance Corporation
(IFC), with about $25 million and a bond underwriter for the remainder.

A bond underwriter was selected and began due diligence. When problems with
the CBE and payments for the electricity arose (see the next section), the bond
underwriter withdrew from the project, leaving a huge hole in the financing. By
this time PowerGen had spent about $100 million on the project.

The IFC agreed to increase its financing to $75 million. The remaining financing
came from six different lenders, with the result that seven different financial closings
were required. Each closing required an entire set of documents (legal opinions,
permits, mortgage registrations, and so forth). As well, it took almost nine months
longer than planned to replace PowerGen’s financial exposure.

Because of all the problems, there was a low level of confidence as to when the proj-
ect would perform. Everyone knew the customer was bankrupt. We were worried that
if we waited one week, the lenders might run away from the project. So, as soon as a
lender said yes, we went to closing. That increased the legal budget exponentially. The
reason the lenders remained in the project was because there was a lot of confidence
in PowerGen and the contractors and there were expectations that the Bamínica
government would stand behind the project.

Richard Jones made our life diffcult because he did not want to trust us, perhaps
because he felt we were not getting the best deal for the joint venture. After we nego-
tiated with the lenders, we often had to negotiate with our own partner about the
financing terms. We had to convince him that it was the best deal for the partnership.
The problem was that our incentives were not aligned properly. From Jones’s point of
view the project was fully financed by PowerGen. He did not have the same incentives
as PowerGen in raising third party debt. If we did not find financing and the project
tanked, PowerGen would have been out of a lot of money. Jones did not have money
in the project to lose. The third party debt was cheaper than PowerGen was charging
the project and, in Jones’s view, PowerGen was benefiting because of this. Every time
something changed he viewed this as an opportunity to improve his position.

The final closing was in April 2006 when lenders assumed the project risk, with
the exception of a PowerGen debt service guarantee of $9.6 million and approxi-
mately $32 million of liability for certain contingent litigation and construction
risk. At this time, total capital in the project was $205 million and the third party
debt portion was $150 million.

692 Part 5 Integrating Case 1

The CBE Does Not Pay
Prior to the start-up of the second phase, there had been some minor disputes
with the CBE about how PJCLP would be paid for the power, about the heat rate,
the cost of fuel, and the measurement of power output. The delayed second phase
start-up increased the contractual diffculties with the CBE. After the second phase
startup in January 2006, the plant performed well for the first month and the
invoice to the CBE became due. By contract, the monthly invoice from simple
cycle to combined cycle went from about $1 million per month to $7 million.
Under the contract, PJCLP had agreed that during the simple cycle phase the
invoice would mainly cover operating costs. Once the second phase was com-
pleted, the capital return and profit billings would begin.

CBE did not have the funds to pay the first invoice. The contract allowed PJCLP
to shut down the plant if payment was not received. PJCLP gave the government
10 days’ notice and then shut down the plant in March 2006. It took 20 days to get
the plant restarted and an agreement reached about payment. In June 2006, a new
government was formed in Bamínica. The outgoing government decided they had
been ill-treated by PJCLP, and again PJCLP was not paid. At this time there were
disputed payments of about $5 million dollars. PJCLP responded by filing an arbitra-
tion claim. By August 2006, the new Bamínica government was in place and had not
yet responded to the claim. In September the government filed a counterclaim. By
the end of 2006, the disputed amount from the PJCLP side was about $19 million.

The problem, according to a PowerGen executive, was as follows:

Under their interpretation of PPAs, the CBE thinks they are entitled to pay based on
what is delivered, notwithstanding a contractual obligation to make capacity payments
and incentives or disincentives regarding the generator’s performance. Even if the shut-
down of the generator was caused by grid failure in Bamínica, they would take the
position that “You are failing to deliver the capacity that we expected and consequently
we are not paying you.”

We concluded that the government and the CBE do not honor their word or the
written contract. They try to find ways to weasel out of it. Part of it is their nature, and
part of it is the fact that they don’t have any money.

In contrast, another PowerGen manager commented:

The contract may have been too overreaching in some areas. For example, was it rea-
sonable to expect them to pay when the plant could not perform? The CBE was an
unsophisticated buyer and did not understand how the PPA really worked.

Throughout this period, management turnover in the CBE did not help:

JI originally signed an agreement with the general administrator of the CBE, who was
authorized by the president to sign a PPA . After we got involved there was a steady
turnover in administrators. Some of them stayed for only a few months. The rumor
was that each administrator signed a project and got a retirement deal. On one occa-
sion we had a Monday meeting with the administrator about an issue that had to be
resolved quickly. As I was having breakfast I read in the local newspaper that Sunday
night the administrator was fired. Now I have a guy who doesn’t know anything about
the deal. I went to his office and he did not want to meet me. He said, “I have been
here for less than 24 hours—I can’t take this to my president.” Did they understand
the contract? Most of them probably never even read it.

According to public statements from the head of the CBE, payments were not
made because the facility had not run up to speed and CBE did not owe nearly as
much as PJCLP claimed. PJCLP was not the only company with which CBE was in

Integrating Case 1 The Bamínica Power Plant Project 693

dispute. Another firm that entered Bamínica about a year after PowerGen threat-
ened to shut down its 220 MW plant because of unpaid bills.

By the end of 2006, an ICC arbitration panel was established, with the arbitra-
tion to take place in Mexico. Meetings with the arbitration panel began in early
2007. All parties agreed on a settlement but in early 2008 the Bamínica govern-
ment changed the CBE management. The new management created a new com-
mittee in charge of negotiating with PJCLP and the new committee refused to
acknowledge any of the earlier negotiations. By the end of 2009, an agreement
was finally reached on the disputed payments.

Settlement with the Contractors
and New Problems
The plant had a series of operating problems from the start-up. Of the five major
pieces of equipment, problems were experienced with each one. In addition to the
start-up problems, a steam turbine blade broke in 2006. In the interim period of
six months between failure and repair, the turbine was run with one less blade,
reducing capacity by 10-15%. By the end of 2006, a settlement was reached with
Western Electric and Sylvanto. These firms agreed to pay for the direct restart
cost and to replace the steam turbine (equipment and installation costs). They
also agreed to an extended warranty on the turbine and boilers. PJCLP and the
contractors also agreed to jointly seek insurance claims and to jointly share any set-
tlement. This agreement was contingent on getting approval from the lenders
because part of the settlement would be release from other claims. PowerGen
thought this was a good deal and asked the lenders for their approval. The new
turbine was scheduled to be installed by April 2007.

The lenders would not approve the settlement. Their view was that there had
been so many problems that they did not want to release anyone. PJCLP decided
that the settlement would go forward without lender approval because it would not
have a material adverse effect on the lenders or the project. The lenders were not
pleased because they hoped PowerGen would come up with additional guarantees,
which PowerGen refused to do. Nevertheless, up to this point, PJCLP had met its
financial obligations to the lenders.

Not long after the settlement with the contractors, the plant began experiencing a
series of tube leaks in both boilers. Each tube leak required the boiler to be shut
down for at least 24 hours of repair. During the repairs it was noticed that there was
buildup of slag on the tubes. The slag blocked the tubes as heat exchangers, which
meant the boilers became less effcient. Various procedures were unsuccessfully tried
to remove the slag, including hydro blasting and chipping the slag off the boilers. As
it turned out, the boilers were not suited to the heavy fuel used by the project because
they were designed for natural gas. Although the slag was common for the fuel used
by PJCLP, the spacing of the boiler tubes must be wide enough to prevent a buildup
on the tubes and cleaning the slag must be possible. The boilers installed had neither
of these features. Unfortunately, PowerGen had no experience with boilers and did
not identify the design problems created by Western Electric and its subcontractors.

The result was that PowerGen began a series of meetings with Sylvanto to deter-
mine how to fix the boilers, which had cost about $6 million. The cost to replace
the boilers was estimated to be about $20 million. Earlier, Sylvanto had informed
PowerGen in writing that the proposed boilers would run on the fuel selected for
the project. When the problems first emerged, Sylvanto’s response was that PJCLP

694 Part 5 Integrating Case 1

was not running the plant properly. Technical consultants were hired to show
that the problem was the boilers, not PJCLP. Finally, the contractors agreed that
the boilers were the wrong type for the fuel. It was not possible to change the
fuel because it would destroy the economic viability of the project. In 2009,
another settlement agreement was being negotiated to get new boilers. PJCLP
would pay the incremental cost of the newly designed boilers (about $4 million)
and the contractors and their insurance carrier would pay an additional $16 million
for installation along with refurbishing the existing boilers in the interim period of
two years.

Richard Jones’s Ownership Is Reduced
The original deal with Richard Jones was that in order to become a 50% share-
holder, he would have to pay cash for 40%. The other 10% would come from his
origination of the deal. At the financial close in April 2006, Jones paid for 5%. An
agreement was reached that gave Jones 18 months to raise $17 million required
for the remaining 35% share. In November 2007, the deadline came and Jones
did not have the money. Jones asked for an indefnite deferral and PowerGen said
no. PowerGen also initiated arbitration with Jones to establish its claim. Jones
countersued and claimed that PowerGen had conspired to prevent him from buy-
ing his share. A six-month arbitration process was resolved in June 2008 when
Jones withdrew his lawsuit and his 35% stake was transferred to PowerGen. Jones
raised another lawsuit in Bamínica alleging that PowerGen fraudulently induced
him to give up his share of the project. Jones claimed damages of $169 million.
In January 2000, the suit was dismissed. In 2011, Jones remained a 15% share-
holder in the joint venture.

Management
Three people reported to the PJCLP executive director: the plant manager, the
financial manager, and the commercial manager. The financial and commercial
managers were Bamínica nationals and had been with PJCLP from the beginning.
The first executive director, hired in September 2006, was an Ecuadorian and for-
mer World Bank employee. He had been the general manager of a utility in Quito.
He was a strong source of technical expertise and understood the IFC. However, he
was not a good politician and was ineffective in building community and government
relations. A new executive director was appointed in January 2008. PJCLP was the new
director’s first assignment in a power company. Prior to PJCLP, the director had been
general manager for several mining companies in Latin America and had worked in
Bamínica. He was strong in building community relations.

Turnover in plant managers was a problem and meant that a long-term opera-
tional strategy was slow to evolve. The first permanent plant manager also began in
September 2006 and was an American of Hispanic origin. He had previously
worked in power plants in Michigan. He was characterized as a “difficult case”
and eventually ended up with little support inside or outside the company. He
was also viewed as a bit scary in that he carried a gun and was suspected of having
a drinking problem. He left voluntarily in January 2008. He was followed by a tem-
porary plant manager who stayed for about three months. In June 2008, another
permanent plant manager was hired. This manager was born in Panama and had
been a plant manager in Argentina and Africa.

Integrating Case 1 The Bamínica Power Plant Project 695

Community Relations
As the payment dispute with CBE increased, CBE used the media aggressively.
PJCLP was blamed for causing major power shortages in Bamínica because of its
operational problems. CBE was able to successfully blunt PJCLP’s efforts to publi-
cize CBE’s poor payment practices by arguing that PJCLP did not deserve to get
paid. To overcome the media campaign, PJCLP began an aggressive community
relations program. According to a PowerGen executive:

Public opinion in Bamínica was not particularly important because the public was pow-
erless. The administration runs the country the way they want to run it. Bad press in the
country does not have much effect on the relationships with the Bamínica government.
Bad press is more important outside the country.

Community relations is another story. We built a relationship with the First Lady, a
woman in her 70s. We were close to the mayor and some of the council members in
Puerto Salinas. We held seminars using people from the university to explain the tech-
nical issues, we invited school children to tour the plant, and we sponsored local sports

EXHIBIT 2
PowerGen/Jones Cogeneration Limited Partnership Balance Sheets December 31, 2009
and 2010

Assets

2010 2009

Current assets:
Cash US$ 9,964,741 US$ 2,296,976
Accounts receivable net of allowance of US$136,198 59,897,787 38,317,364
Inventories, mainly fuel and parts 4,577,327 3,447,421
Prepaid insurance 894,293 1,347,472

Total current assets 75,334,148 45,409,233

Pre-operating expenses 17,542,651 18,661,923
Property, plant and equipment 175,483,806 180,717,632

193,026,457 199,379,555
US$268,360,605 US$244,788,784

Liabilities and Partnership Equity

Current liabilities:
Current portion of long-term debt US$ 15,077,649 US$ 13,336,312
Accounts payable 16,858,589
Accounts payable to related companies 19,158,511 21,633,360
Accrued interest payable 4,809,250 1,512,285
Other accrued liabilities 4,702,396 3,093,830

Total current liabilities 60,606,395 39,575,787

Deferred income from capacity fees 5,780,049 2,709,201
Long-term debt 135,066,438 143,915,521

140,846,487 146,624,722

Partnership equity:
Partner contributed capital 51,077,600 51,077,600
Undistributed partnership earnings 15,830,123 7,510,679

Total equity 66,907,723 58,588,279
US$268,360,605 US$244,788,788

696 Part 5 Integrating Case 1

teams. We did some training with the fire department. We bought some used fire
equipment and clothing from a fire company in Fort Worth and gave it to the fire depart-
ment. We bought tires for the ambulance. When we bought emergency equipment for
the plant, I bought two of everything and gave half to the ambulance service. This was
all done very quietly.

Unfortunately, after the project was transferred to the PowerGen operators, commu-
nity relations efforts did not improve. No natural allies were created to carry us through
good and bad times. The thought was, “We have an operating project. We have to go
run it just as we would in the States.”

Hotel Claims
During the construction period, the adjacent hotel initiated a lawsuit against the
noise. The lawsuit was settled with a payment of $1 million by PJCLP in 2005. Dur-
ing the construction of the second phase, the hotel began losing customers. In
2007, the hotel was permanently closed. The hotel owners, a wealthy and well-
connected Bamínica family, filed an arbitration claim against PJCLP claiming that
the plant had been built illegally and that the plant site should never have been
developed as an industrial site. The claim maintained that the permits from the
government had been given improperly.

The acknowledged cost and value of the hotel, even according to the hotel
accountants, was not more than $5 million. In 2008, a Bamínica arbitration panel
awarded the hotel $13.6 million against the project. The panel had three members

EXHIBIT 3
PowerGen/Jones Cogeneration Limited Partnership Statements of Income and
Undistributed Partnership Earnings Year Ended December 31, 2009 and 2010

2010 2009

Income:
Energy income US$ 51,552,207 US$ 46,655,458
Capacity, operation and maintenance fees 38,566,090 37,049,085

Total revenues 90,115,297 83,704,543

Cost and expenses:
Operating costs 46,865,643 42,682,139
Depreciation of machinery and equipment 5,667,430 5,367,238
Amortization of prepaid insurance 2,217,571 2,066,118
Amortization of pre-operating expenses 1,134,984 970,878
Administrative expenses 12,322,451 9,817,533

68,208,079 60,903,906
Net operating income 21,910,218 22,800,637

Interest income 4,819,080 1,786,228
Interest expense (18,398,256) (17,032,683)
Exchange loss (11,598) (31,783)
Other (11,720)

Other income (expenses) (13,590,774) (15,289,958)

Net income 8,319,444 7,510,679
Undistributed partnership earnings at the beginning of year 7,510,679

Undistributed partnership earnings at the end of year US$ 15,830,123 US$ 7,510,679

Integrating Case 1 The Bamínica Power Plant Project 697

but before the decision was complete, the chairman of the panel was appointed to
the Bamínica Supreme Court. By law, the chairman was unable to participate in
the arbitration. The remaining two panelists completed the arbitration. PJCLP
appealed the arbitration ruling in the Bamínica courts, claiming that without a
third panelist, the arbitration was invalid according to Bamínica rules of arbitra-
tion. In 2011, the arbitration was not settled.

The Project in 2011
Looking forward, Tom Stephens hoped to take advantage of the learning from the
Bamínica project. One of the interesting outcomes was that despite all the pro-
blems and challenges, the project was profitable (see Exhibits 2 and 3 for project
financial statements). Perhaps a key lesson was to take a long-term view and not let
any one issue derail the entire project.

C A S E D I S C U S S I O N Q U E S T I O N S

1. Discuss some of the major challenges that PowerGen
faced as they developed the Baminica Power Plant
project.

2. What factors can explain these challenges? Were these
challenges due solely to institutional or cultural factors?

3. What went wrong when PowerGen was negotiating
with Richard Jones? Did Richard Jones use any of

the dirty negotiation tactics discussed in the negotia-
tion chapter?

4. What steps should PowerGen have taken to ensure
that the negotiations went smoothly? Why did they
agree to the partnership despite the problems?

5. What would you do now? Would you end the
project?

698 Part 5 Integrating Case 1

Calculate your order
Pages (275 words)
Standard price: $0.00
Client Reviews
4.9
Sitejabber
4.6
Trustpilot
4.8
Our Guarantees
100% Confidentiality
Information about customers is confidential and never disclosed to third parties.
Original Writing
We complete all papers from scratch. You can get a plagiarism report.
Timely Delivery
No missed deadlines – 97% of assignments are completed in time.
Money Back
If you're confident that a writer didn't follow your order details, ask for a refund.

Calculate the price of your order

You will get a personal manager and a discount.
We'll send you the first draft for approval by at
Total price:
$0.00
Power up Your Academic Success with the
Team of Professionals. We’ve Got Your Back.
Power up Your Study Success with Experts We’ve Got Your Back.

Order your essay today and save 30% with the discount code ESSAYHELP